The total float of activity E in the diagram is:

Prepare for the APM Project Fundamentals Qualification Exam with comprehensive questions and detailed explanations. Enhance your project management skills and succeed on exam day!

To determine the total float of activity E, it is essential to first understand the concept of total float in project management. Total float, also known as total slack, refers to the amount of time that a task can be delayed without causing a delay to the project's overall timeline or the start of a subsequent task.

In this context, if the correct answer indicates that the total float for activity E is 2, it implies that activity E has some flexibility in its scheduling. Specifically, it can be delayed by up to two time units without affecting the completion date of the project or other dependent activities. This situation usually arises when there is slack in the project schedule, often due to a combination of activities being sequenced in such a way that not all of them have to be started or completed immediately.

To accurately assess the total float for any activity, one would typically evaluate the earliest start time, the latest start time, the duration of the activity, and the overall project timeline. A total float of 2 suggests that there is enough leeway in the scheduling of activity E, allowing the project manager to potentially reallocate resources or shift tasks without jeopardizing the completion date.

Understanding total float is crucial for effective project scheduling and resource management, as it helps